Last week was quite busy for me, as Alex was on vacation for
a few days, so I had to take care of doing our meeting minutes, SOP cards, the
daily report, and all of our normal duties by myself. I was also tasked with
picking out appliances that meet GM’s specifications and getting product data
on them for a submittal. We sent in the submittal on Wednesday, and everything
was approved. Now we have to coordinate with our subs to get all of the proper plumbing
and electrical in place so that all of the appliances can be installed.
The schedule at building 70 is moving along as planned, and
we are finished with framing walls, and are almost finished with drywall. Our
carpenters have started to frame the ceilings, and Ensroth is making more and
more progress with the ductwork and fire dampers. We have painters on site, and
they have a coat of primer on most of the walls on the East end of the building,
and they have started to repaint one of the stairwells. We also had some guys
from Gardiner Voss on site for a few days to install the support steel for the
operable partition in one of the conference rooms. In addition to all of this,
VAV boxes are getting piped and wired, and we have three drywall finishers
working hard to get our walls ready for paint. It is very interesting to watch
them work, as they have a few specialized tools that enable them to work
extremely fast.